Consider the order-requirement digraph above, where all indicated weights are in minutes. Using the critical-path scheduling method, schedule the 7 tasks on 3 processors. Enter the task labels and idle times (if any) in order for each processor, separated by commas. For example: 3,T1,T2,4,T5,6
Processor 1 : Processor 2 : Processor 3 :